The 1.5 metre rule, when a balustrade is required, and what else Rodney homeowners should check before building a deck.

Most decks in the Auckland region, including all of Rodney, can be built without a building consent. The test is height. If nobody could fall more than 1.5 metres from the deck, it is exempt under Schedule 1 of the Building Act.

The 1.5 metre rule

The measurement is the fall height: the distance from the deck surface to the ground below at the highest point. On a sloping section a deck can be level with the lawn at the house and well over 1.5 metres up at the far edge. It is the highest point that counts.

If the fall is more than 1.5 metres, you need a building consent from Auckland Council before work starts. That means drawings, a processing period and inspections during the build.

Exempt does not mean no rules

A deck that does not need a consent still has to comply with the Building Code. In practice that covers three things:

  • Structure. Piles, bearers and joists sized and spaced correctly for the span and the load.
  • Durability. The right timber treatment for each part, and fixings suited to the site. Near the coast that usually means stainless steel.
  • Safety from falling. A barrier at least 1 metre high wherever the fall is 1 metre or more.

The gap between 1 metre and 1.5 metres

This catches people out. A deck with a fall of 1.2 metres does not need a consent, but it does need a compliant balustrade. If you want an open-edged deck with no rail, keep the fall under 1 metre.

Other rules that can apply

  • District plan rules. The Auckland Unitary Plan sets limits on things like how close structures can be to a boundary and how much of the site can be covered. These are separate from the building consent question.
  • Roofs. Adding a roof over a deck changes the picture. Small roofed structures can be exempt, larger ones need a consent.
  • Pools and spas. Decks that form part of a pool barrier have their own rules and are inspected by council.
  • Covenants. Newer subdivisions such as Millwater often have covenants that restrict what you can build.

What to do

Measure the highest point of the planned deck above the ground. Under 1 metre is the simplest case. Between 1 and 1.5 metres, budget for a balustrade. Over 1.5 metres, allow extra time and money for a consent. A local deck builder will confirm which applies at the quote visit.

This guide is general information, not advice on your specific site. Rules change, so confirm consent requirements with Auckland Council or your builder before you start.